Project Case Study · Industrial Steel & Audit
Al Barakah Marquee (PEB Structure)
35+ MT
Structural Steel Erection
100% Verified
Weight Slips & Ultrasonic Weld QC
PKR Millions
Client Cost Savings via Audit Reconciliation
AISC 360
Structural Steel Compliance
The Al Barakah Marquee project highlights Fusion Developers' dual capabilities in heavy structural steel engineering and forensic construction cost auditing. In addition to delivering the structural engineering design and on-site QC supervision for over 35 metric tons of structural steel, our team was engaged to conduct a comprehensive financial statement reconciliation and contractor audit of the SBW Engineering account.
Structural Engineering & Fabrication Oversight
The structure utilizes portal-frame PEB design engineered to withstand severe wind loads and seismic accelerations. Our site engineers conducted ultrasonic non-destructive testing (NDT) on full-penetration butt welds, certified high-strength bolt torque calibrations, and verified plumbness of all erected columns.
Forensic Contract Audit & Material Reconciliation
When contractor billing discrepancies arose, Fusion Developers performed a forensic audit cross-referencing 60+ verified certified weighbridge weight slips, mill test certificates, and actual measured on-site steel tonnage. Our audited reconciliation dossier eliminated millions in unwarranted duplicate billing and established transparent contract closure under Pakistani engineering standards.
Key Quantities & Project Metrics
- Primary Frame Steel Tonnage:35.80 Metric Tons
- Secondary Framing (Z & C Galvanized Purlins):12.40 Metric Tons
- High-Strength Fasteners (Grade 8.8):1,850 Units
- Audited Weight Slips Reconciled:60+ Certified Slips